CC-J: Construction Plan
JFY 1998 (Apr. 1998 - Mar. 1999)
- Tape robot(200 TB), HPSS will be installed in Jan.’99
- Prototype of Data Duplicating Facility &
- Prototype of Simulation and Analysis Hardware
- are going to be installed at RBRC at BNL for R&D
Under the current budget plan
- JFY 1999 (Apr. 1999 - Mar. 2000)
- 1/3 scale of the system will be completed.
- Hopefully start operation in the end of 1999
- JFY 2000 (Apr. 2000 - Mar. 2001)
- 2/3 scale of the system will be completed.
- JFY 2001 (Apr. 2001- Mar. 2002)
- Full scale of the system will be completed.